What is a key advantage of the CM at-Risk delivery method from the owner's perspective compared to traditional Design-Bid-Build?
-
A
The CM performs all design work in-house, eliminating architect fees
-
B
The CM provides preconstruction services and cost input during design, improving constructability
-
C
The owner retains no financial risk because the CM assumes all project liability
-
D
Competitive bidding is eliminated entirely, reducing procurement time to days