A CM discovers that a subcontractor has falsified daily reports to conceal a schedule delay. What is the CM's primary ethical obligation?
-
A
Confront the subcontractor privately and allow them to self-correct
-
B
Report the falsification to the owner and document the incident formally
-
C
Ignore it if the project recovers on schedule
-
D
Notify only the general contractor and let them handle it