A construction manager conducts a 'constructability review' during design. What is the primary cost management benefit?
-
A
It allows the owner to reduce the project scope
-
B
It identifies construction issues early when changes are least expensive to make
-
C
It replaces the need for contractor bids
-
D
It establishes the final project schedule baseline