A construction manager notices activities on the critical path have zero total float. A non-critical activity has 5 days of total float consumed. What is the impact?
-
A
The project end date is immediately delayed by 5 days
-
B
The activity's float buffer is reduced but project end date is unaffected unless all float is consumed
-
C
The critical path changes automatically
-
D
The activity becomes a milestone