What does a Schedule Performance Index (SPI) of 1.15 indicate about a construction project?
-
A
The project is 15% over budget
-
B
The project is completing 15% more work than planned per time period
-
C
The project is 15% behind schedule
-
D
The project has 15% contingency remaining