A contractor submits a pay application that includes costs for stored materials not yet incorporated into the work. Under what condition should the CM certify payment for these materials?
-
A
Never โ payment is only for work in place
-
B
Only if the materials are stored on-site and properly protected
-
C
Only if the owner has approved the stored materials provision in the contract
-
D
Only if the materials are stored off-site in a bonded warehouse