In the context of construction risk, 'force majeure' events are best described as:
-
A
Risks caused by contractor negligence
-
B
Unforeseeable events beyond the parties' control that excuse contract performance
-
C
Delays resulting from subcontractor default
-
D
Owner-directed changes to the project scope