A project has a contract value of $10M, with $6M of work complete but only $5M earned. The actual cost to date is $5.5M. What is the project's current status?
-
A
Over budget and behind schedule
-
B
Under budget and ahead of schedule
-
C
Over budget and ahead of schedule
-
D
Under budget and behind schedule