What is the Critical Path Method (CPM) used for in construction project management?
-
A
Tracking material procurement costs against budget
-
B
Identifying the longest sequence of dependent activities that determines project duration
-
C
Conducting safety inspections at critical project milestones
-
D
Reviewing contract documents for critical risk provisions