What is the 'critical path' in project management?
-
A
The most expensive sequence of project tasks
-
B
The longest sequence of dependent tasks that determines the minimum project duration
-
C
The sequence of tasks most likely to face delays
-
D
The path taken by the project manager during oversight visits