When steam piping is first pressurized after installation or repair, why is a slow, controlled warm-up procedure a critical risk mitigation step?
-
A
To allow paint on the pipe surface to cure properly
-
B
To prevent thermal shock and condensate water hammer as cold pipe heats gradually
-
C
To give inspectors time to complete paperwork before full pressure is reached
-
D
To reduce noise levels during startup