You are a project manager with two deliverables due on the same day. One is for a key client worth significant revenue, and the other is an internal report your director requested last week. You can only fully complete one. What is the most appropriate action?
-
A
Complete the internal report first since your director outranks the client
-
B
Complete the client deliverable and inform your director early that the internal report will be slightly delayed
-
C
Ask a colleague to submit the internal report without telling your director
-
D
Request a deadline extension from the client to prioritize the internal report