A stakeholder asks the Product Owner to reorder the Product Backlog. What should the Product Owner do?
-
A
Consider the input but retain accountability for ordering
-
B
Immediately comply without question
-
C
Delegate the decision to the Scrum Master
-
D
Refuse all stakeholder input