Project Management Flashcards
6 cards from real RICS APC practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Project Management flashcards as text
What is a 'programme' in the context of construction project management?
Answer: A schedule showing the planned sequence, duration, and timing of construction activities
In UK construction, a programme (schedule) shows the planned sequence of activities, their durations, dependencies, milestones, and critical path for the project.
Under the CDM Regulations 2015, who is the 'Principal Designer'?
Answer: The designer appointed by the client to plan, manage, monitor, and coordinate health and safety during the pre-construction phase
Under CDM 2015, the Principal Designer is appointed by the client to plan, manage, and coordinate health and safety matters during the pre-construction phase, ensuring design risks are managed.
What is 'float' in a project schedule?
Answer: The amount of time a non-critical activity can be delayed without affecting the project completion date
Float (or slack) is the amount of time a non-critical activity can be delayed or extended without delaying the overall project completion date. Critical path activities have zero float.
What is a 'clerk of works' role on a construction project?
Answer: To act as the client's on-site representative, inspecting work quality and compliance with specifications
A clerk of works is an independent professional employed by the client to be present on site, inspecting the quality of workmanship and materials to ensure compliance with contract documents.
What does 'procurement' mean in the context of a construction project?
Answer: The overall process of acquiring construction services, including selecting the contract strategy, tendering, and appointing contractors
Procurement in construction encompasses the entire process of selecting the appropriate contract strategy, inviting and evaluating tenders, and appointing the contractor(s) to deliver the project.
What is the purpose of a 'pre-construction services agreement' (PCSA)?
Answer: To engage a contractor early to provide input on buildability, programming, and cost during the design phase before the main contract is let
A PCSA allows a client to engage a contractor during the design stage to provide early input on buildability, sequencing, cost planning, and risk, before committing to a full construction contract.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- rics.org — Exam dates, registration, retake fee, fees, eligibility, renewal, retake policy, score validity, test delivery, exam format · verified Oct 2026