Read the first 7 Building Surveying & Construction flashcards as text
What is the generally accepted minimum height of a damp-proof course above external ground level?
Answer: 150mm
A DPC should be at least 150mm above external ground to prevent rain splash and ground moisture bridging it.
In which units is a U-value expressed?
Answer: W/m²K
A U-value is the rate of heat transfer through one square metre of an element per degree of temperature difference.
To reduce the risk of interstitial condensation in an insulated timber frame wall, the vapour control layer should usually go:
Answer: On the warm (internal) side of the insulation
A VCL on the warm side stops moist internal air reaching cold surfaces inside the wall, where it would condense.
Why is lime mortar usually specified when repointing pre-1919 solid brick walls?
Answer: It is breathable, flexible and sacrificial, so it protects softer historic bricks
Lime lets moisture evaporate through the joints and takes up movement, so the mortar weathers instead of the brick.
Reinforced Autoclaved Aerated Concrete (RAAC) planks, now a widely reported defect, were mainly used in which elements of UK public buildings?
Answer: Flat roofs, and sometimes floors and walls, from the 1950s to the mid-1990s
RAAC is lightweight and porous with a limited life span and was used mainly for flat roof planks in schools and hospitals between the 1950s and 1990s.
High alumina cement (HAC) concrete used in 1950s–1970s pre-stressed beams is a concern mainly because of:
Answer: Conversion, which leads to loss of strength over time
HAC undergoes mineralogical conversion, particularly in warm, damp conditions, which makes it more porous and weaker.
Mundic block, a defect that can make properties unmortgageable, is mainly found in which part of the UK?
Answer: Cornwall and parts of Devon
Mundic concrete contained mine waste aggregate that can break down, and RICS guidance sets out a screening and classification process for it.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- rics.org — Eligibility, renewal, retake policy, score validity, exam dates, registration, retake fee, test delivery, exam format, score release · verified Nov 2026