What is the primary difference between validation and verification in project quality?
-
A
Verification checks that work is built correctly; validation checks that the right work was built
-
B
Validation is done internally; verification is done by the customer
-
C
Verification occurs only at project end; validation occurs throughout
-
D
Validation applies only to software projects; verification applies to all projects