7 cards from real Program Management Professional practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Trivia flashcards as text
  1. Ann is the ABC Program's program manager. A vendor just finished the job he was hired to complete for her program. Ann agrees that the job has been completed, so what document should you and the vendor sign now?

    Answer: Certificate of completion

    A certificate of completion is a formal document signed by both the buyer (program manager) and the seller (vendor) to acknowledge that the contracted work has been satisfactorily finished. This document signifies the formal closure of the contract and confirms that all deliverables have been met according to the agreed-upon terms. It's a crucial step in formalizing the end of a procurement relationship.

  2. Sheila is the program manager of the company. Management has requested her to evaluate when resources, such as leased equipment, are no longer required so that she may release them to save time, money, and resource usage within the program. What program management process is management requesting from Sheila?

    Answer: Resource control

    Resource control involves ensuring that the physical resources assigned to the program are available as planned and are used efficiently. This includes monitoring resource utilization, managing resource allocation, and releasing resources when they are no longer needed. Sheila's task of evaluating when leased equipment can be released directly aligns with optimizing costs and resource availability for other projects or programs, which are objectives of resource control.

  3. Rhonda works as the program manager for her company. She is working on a paper that will outline the benefits the program will provide to her organization once it is done. What is Rhonda working on?

    Answer: Program benefits statement

    A program benefits statement is a document that clearly articulates the measurable benefits that the program is expected to deliver to the organization upon its completion. It outlines how the program will contribute to strategic objectives and provides a basis for evaluating the program's success. This statement is distinct from a program charter (which authorizes the program) or a benefits realization plan (which details how benefits will be achieved and measured).

  4. Tina manages programs at the organization. She is reviewing the activities in your program schedule and would like to adjust some of the ordering to avoid scheduling conflicts, concerns, and based on your expertise with the discipline the program utilizes. Some of the exercises she can change, while others must be performed in a specific order. What phrase best represents actions that can occur in any order?

    Answer: Mandatory dependencies

    Discretionary dependencies, also known as preferred or soft logic, are relationships between activities established based on best practices, historical information, or the project team's expertise. Unlike mandatory dependencies (which are legally or physically required), discretionary dependencies can be changed or adjusted by the project manager to optimize the schedule, avoid conflicts, or improve efficiency. The question describes activities that 'she can change' based on expertise, fitting the definition of discretionary dependencies.

  5. Karen works as the OFE Program's program manager. She collaborates with the program team and project managers to ensure that the program plan is followed consistently. Karen emphasizes that the job has been scheduled and that the team must now perform it correctly. She wants to make certain that the work in the application is done correctly the first time. Which type of process is she stressing to her program team and project managers?

    Answer: Quality assurance

    Karen's emphasis on ensuring the program plan is followed consistently and that work is done correctly the first time aligns directly with Quality Assurance. Quality Assurance focuses on preventing defects by ensuring that the processes used to create deliverables are effective and followed correctly. It's a proactive approach to build quality into the process, rather than just inspecting the final product.

  6. Rex is the organization's project manager, and he is working with the project stakeholders and the business analyst to identify all of the deliverables that the project will provide. The stakeholders would like to be able to add more deliverables later in the project while keeping the requirements reasonably flexible. Rex informs the business analyst that he needs a set of criteria that outline precisely what must be provided for the project. In this early stage of the project, what document is he trying to create?

    Answer: Project scope statement

    Rex is in the early stages of identifying all deliverables and needs a document outlining precise criteria for what must be provided, despite stakeholders wanting flexibility. The Project Scope Statement is the document that defines the project's scope, including deliverables, requirements, boundaries, and acceptance criteria. It provides the necessary detail and precision for what the project will produce.

  7. The organization's program manager is Tony. Management is thinking about starting a new program, but they are concerned about the program risks that might affect its success. Tony is aware that any danger might have three positive risk responses and three negative risk responses. Management asks him which risk response would be best for a significant risk event if the program wants to engage a third-party to own the risk event. What is the most suitable risk event?

    Answer: Transference

    Risk transference involves shifting the ownership and impact of a risk to a third party, often through insurance, contracts, or outsourcing. In this scenario, engaging a third-party to 'own the risk event' is a direct example of transference. This strategy allows the program to offload the responsibility and potential consequences of a significant risk.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy