What is the key difference between 'Consulted' and 'Informed' roles in a RACI matrix?
-
A
Consulted stakeholders receive final reports; Informed stakeholders give approvals
-
B
Consulted involves two-way input before decisions; Informed means one-way updates after decisions
-
C
Consulted stakeholders are internal only; Informed stakeholders can be external
-
D
There is no meaningful operational difference between the two designations