Procore Superintendent Change Order Management Flashcards

7 cards from real Procore Superintendent Certification practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.

Read the first 7 Procore Superintendent Change Order Management flashcards as text
  1. In Procore, who typically has authority to approve a Prime Contract Change Order (PCCO)?

    Answer: The owner or owner's authorized representative

    Prime Contract Change Orders modify the value of the prime contract and therefore require approval from the owner or their authorized representative.

  2. What Procore feature allows a superintendent to formally request pricing from subcontractors when evaluating the cost of a potential change?

    Answer: Request for Quote (RFQ) within the PCO or Change Event

    Procore's change management module allows RFQs to be sent directly to subcontractors from within a PCO or Change Event to formally gather pricing.

  3. When an owner issues a Change Directive requiring the superintendent to proceed with work before pricing is agreed upon, what is the best practice in Procore?

    Answer: Document the directive as a PCO and track actual costs using time and materials (T&M) methods

    A Change Directive requires proceeding with work; documenting it as a PCO with T&M cost tracking protects the contractor's entitlement to full compensation.

  4. In Procore's change management module, what does the term 'markup' refer to when building a change order estimate?

    Answer: The percentage added to direct costs for overhead and profit

    In Procore change orders, markup is the percentage added on top of direct labor, material, and equipment costs to cover overhead and profit.

  5. A superintendent needs to formally adjust a subcontractor's scope and cost because of an owner-directed addition. Which Procore document type should be created?

    Answer: Commitment Change Order (CCO)

    A Commitment Change Order (CCO) is the Procore document used to formally modify a subcontract or purchase order when scope or cost changes occur.

  6. What is the purpose of linking a PCO to a specific cost code in Procore?

    Answer: To track the financial impact of the change against the correct budget line item

    Linking a PCO to a cost code ensures the financial impact of the change is tracked against the correct budget category, enabling accurate cost reporting and forecasting.

  7. In Procore, which change order status indicates the change has been fully executed by all parties and the contract value has been officially updated?

    Answer: Approved

    An 'Approved' status in Procore confirms the change order has been executed by all required parties and the contract value is officially adjusted.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. procore.com — Eligibility · verified Oct 2026
  2. support.procore.com — Score validity, renewal · verified Oct 2026