  1. In Procore, what is the first step a superintendent typically takes when a change in scope is identified in the field?

    Answer: Create a Potential Change Order (PCO)

    A Potential Change Order (PCO) is the first document created in Procore to capture and track a scope change before it becomes a formal change order.

  2. Which Procore document allows a superintendent to capture field-identified scope changes and link them to cost codes and budget line items?

    Answer: Potential Change Order (PCO)

    Potential Change Orders (PCOs) in Procore allow superintendents to capture field changes and associate them with cost codes and budget line items for tracking.

  3. When a superintendent receives a verbal instruction from the owner to proceed with extra work, what is the best practice in Procore?

    Answer: Document the verbal instruction in a PCO immediately

    Verbal instructions should be immediately documented in a PCO to create a contemporaneous paper trail and protect the contractor's right to compensation.

  4. In Procore's change management workflow, what is the correct order of change order documents from initial identification to final execution?

    Answer: PCO → CCO → Prime Contract Change Order

    Procore's change management workflow flows from PCO (internal capture) to CCO (subcontractor-level adjustment) to Prime Contract Change Order (owner-level execution).

  5. A superintendent notices a subcontractor has performed extra work not included in the original scope. What is the correct action in Procore?

    Answer: Create a PCO and send a Request for Quote (RFQ) to the subcontractor

    Creating a PCO and requesting a quote from the subcontractor formalizes the scope change and ensures proper cost tracking before billing or approval.

  6. Which Procore feature provides real-time visibility into the financial impact of pending and approved change orders on the overall project budget?

    Answer: Budget tool with change order integration

    Procore's Budget tool integrates directly with the change management module to display real-time cost impacts from both pending and approved change orders.

  7. What does a 'pending' status on a change order in Procore indicate?

    Answer: The change order has been submitted but not yet approved by the receiving party

    A 'pending' status in Procore means the change order has been submitted to the relevant party (such as the owner) but their approval has not yet been received.

  8. When tracking time and materials (T&M) work for a potential change order, what should a Procore superintendent document daily?

    Answer: Labor hours, material quantities, and equipment usage with supporting photos and receipts

    Daily T&M tracking requires documenting all cost components—labor hours, material quantities, and equipment usage—with supporting documentation to fully substantiate the change order.

  9. Which Procore module is most effective for documenting unforeseen field conditions (such as buried utilities or differing site conditions) that may justify a change order?

    Answer: Daily Log with photos and field notes

    The Daily Log in Procore allows superintendents to document field conditions contemporaneously with photos and notes, creating the evidentiary foundation for a change order claim.

  10. How does an approved change order affect the project budget in Procore?

    Answer: It adjusts the revised contract value and updates the corresponding budget line items

    Approved change orders in Procore update the revised contract value and adjust the corresponding budget line items to reflect the new authorized scope and cost.

  11. What is the primary benefit of attaching supporting documentation (photos, sketches, emails) to a PCO in Procore?

    Answer: It provides substantiation for the change and protects against scope or cost disputes

    Attaching supporting documentation to a PCO in Procore creates a comprehensive, auditable record that substantiates entitlement and helps resolve potential disputes.

  12. A superintendent determines that a change order will extend the project completion date. What should be included in the PCO in Procore?

    Answer: Both the cost impact and a request for a time extension reflecting the schedule impact

    PCOs should capture both cost and schedule impacts to ensure the contractor is compensated for additional costs and protected against liquidated damages for the delay.

  13. In Procore, what does a 'disputed' status on a change order indicate?

    Answer: The parties disagree on the pricing, scope, or entitlement of the change

    A 'disputed' status in Procore indicates that the parties involved cannot reach agreement on some aspect of the change order, such as cost, scope, or whether the change is entitled.

  14. According to Procore change management best practices, when should a superintendent create a PCO relative to when the changed work is performed?

    Answer: As early as possible—ideally before or immediately when the change is identified

    Creating a PCO as early as possible ensures timely notice to the owner, proper documentation, and preservation of the contractor's contractual right to compensation.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. procore.com — Eligibility · verified Oct 2026
  2. support.procore.com — Score validity, renewal · verified Oct 2026