  1. What is the purpose of the submittal process in a construction project managed with Procore?

    Answer: To verify that proposed materials and methods comply with the contract documents before installation

    Submittals ensure that materials, equipment, and methods proposed by the contractor match what is specified in the contract documents before they are installed.

  2. In Procore, who is typically responsible for creating and managing the submittal log?

    Answer: The project manager or superintendent, often with help from the project engineer

    The GC's project manager or superintendent, often supported by a project engineer, is responsible for initiating and tracking submittals in Procore.

  3. What does a 'Revise and Resubmit' response on a submittal mean for the superintendent?

    Answer: The submitted material or shop drawing does not fully comply and must be corrected and resubmitted before procurement or installation

    'Revise and Resubmit' means the design team found non-compliance issues that must be corrected before the material can be approved for use.

  4. How does Procore's submittal log help a superintendent manage long lead-time items?

    Answer: By tracking required dates and approval deadlines, the superintendent can identify items that need early procurement to avoid schedule delays

    Tracking submittal deadlines against the schedule helps the superintendent identify long lead-time items that require early action to prevent delays.

  5. What information should a superintendent verify before allowing a subcontractor to install a material tied to an open submittal?

    Answer: That the submittal has been formally approved or approved with comments in Procore

    A material should not be installed until its submittal has received formal approval or 'approved as noted' status from the design team.

  6. In Procore, what does linking a submittal to a specific specification section accomplish?

    Answer: It creates a traceability connection between the submittal and the contract requirement it is meant to satisfy

    Linking submittals to specification sections makes it easy to verify that all specified requirements have been addressed and creates a complete compliance record.

How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy

Sources & references

Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy

  1. procore.com — Eligibility · verified Oct 2026
  2. support.procore.com — Score validity, renewal · verified Oct 2026