What is a 'shop drawing' in the context of construction submittals?
Answer: A drawing prepared by a subcontractor or supplier showing fabrication, assembly, or installation details for a specific scope of work
Shop drawings are detailed fabrication or installation drawings prepared by subcontractors or suppliers to show how they will build or install their scope of work.
In Procore, what is the difference between a 'submittal' and a 'submittal package'?
Answer: A submittal is a single item for review while a submittal package groups related submittals that should be reviewed together
Submittal packages in Procore allow related items — such as all submittals for a mechanical system — to be grouped for simultaneous design team review.
What does the 'ball in court' field on a Procore submittal indicate?
Answer: Which party — contractor, subcontractor, or design team — currently has responsibility for the next action on the submittal
The 'ball in court' field prevents submittals from getting lost by always identifying the party responsible for the next action.
When a design team approves a submittal 'with comments,' what should the superintendent do before allowing installation?
Answer: Review the comments carefully and ensure all conditions noted by the design team are incorporated into the work
'Approved with comments' means the submittal is conditionally approved; the noted conditions must be incorporated or the approval may be invalidated.
Why is it important for the superintendent to track submittal review turnaround times in Procore?
Answer: To identify design team review delays that may entitle the contractor to a time extension under the contract
Contracts typically allow a defined number of days for submittal review; tracking turnaround times documents potential owner-caused delays for time extension claims.
What does the specification 'Division 01' (General Requirements) typically govern regarding submittals?
Answer: It establishes the procedures, formats, and schedule for the entire submittal process on the project
Division 01 General Requirements sets the rules for submittals — who submits them, timelines, formats, and the review process applicable to all divisions.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- procore.com — Eligibility · verified Oct 2026
- support.procore.com — Score validity, renewal · verified Oct 2026