What is the purpose of the Lessons Report produced during Managing a Stage Boundary?
-
A
To document the financial performance of the completed stage
-
B
To pass on useful lessons so they can benefit the current project or future projects
-
C
To record all issues raised during the stage for the issue register
-
D
To report individual team member performance to the Project Board