A scheduler uses 'Schedule Compression' tools within the software. Which two techniques are most commonly supported for compressing a schedule without changing scope?
-
A
Resource leveling and lag adjustment
-
B
Fast tracking and crashing
-
C
Monte Carlo simulation and PERT
-
D
Lead time reduction and constraint removal