A project scheduler identifies a near-critical path with only 2 days of total float. What is the most appropriate action?
-
A
Ignore it as it is not on the critical path
-
B
Monitor it closely as it could become critical if delays occur
-
C
Add resources immediately to eliminate all float
-
D
Convert its dependencies to mandatory constraints