When a project schedule shows negative float on the critical path, the scheduler should:
-
A
Immediately notify the project sponsor and close the project
-
B
Analyze options to compress the schedule or revise constraints
-
C
Remove all lags from the network
-
D
Convert all dependencies to Finish-to-Start relationships