A scheduler needs to shorten the schedule without adding resources. Which approach should be considered first?
-
A
Crashing critical path activities
-
B
Fast tracking activities currently done in sequence
-
C
Removing low-priority activities from scope
-
D
Reducing quality requirements on deliverables