A project scheduler uses resource leveling on a project with a fixed end date. What is the most likely outcome?
-
A
The project end date is extended beyond the constraint
-
B
Resource peaks are smoothed without changing the end date
-
C
Resource usage is optimized while the end date may slip
-
D
Activities are split to stay within the fixed deadline