Which of the following BEST distinguishes fast tracking from crashing in terms of project risk?
-
A
Fast tracking increases cost risk; crashing increases rework risk
-
B
Crashing increases cost risk; fast tracking increases rework and coordination risk
-
C
Both techniques equally increase scope risk
-
D
Crashing increases schedule risk; fast tracking eliminates it