A project manager is comparing the cost of crashing with the penalty for being late. Crashing costs $5,000 per day and the late penalty is $8,000 per day. What is the BEST decision?
-
A
Do not crash because it increases project cost
-
B
Crash the schedule because it is cheaper than the late penalty
-
C
Fast track instead to avoid all costs
-
D
Extend the deadline to eliminate the penalty