A project manager is crashing a construction project. After crashing activity X by 2 days, the critical path shifts to a new path. What should the project manager do next?
-
A
Stop crashing since the original critical path is now compressed
-
B
Recalculate the network and crash activities on the new critical path
-
C
Apply fast tracking to all remaining activities
-
D
Update the cost baseline to reflect crashing costs