A project manager needs to recover 3 weeks on a software project. After analyzing the schedule, she identifies that adding developers to the coding phase will reduce duration but increase cost. This is an example of which compression technique?
-
A
Fast tracking
-
B
Crashing
-
C
Resource leveling
-
D
Schedule baselining