A project team identifies a risk that has a high probability of occurring but decides to accept it because the cost of mitigation exceeds the cost of the delay. This is an example of:
-
A
Risk avoidance
-
B
Active risk acceptance with a contingency plan
-
C
Passive risk acceptance
-
D
Risk escalation to the program manager