A project scheduler performs quantitative risk analysis and determines the project has a 40% chance of meeting the baseline completion date. The sponsor requires 90% confidence. What action is MOST appropriate?
-
A
Report to the sponsor that 40% is acceptable industry standard
-
B
Add schedule contingency reserves until the model shows 90% confidence
-
C
Remove activities from the critical path to reduce duration
-
D
Switch from quantitative to qualitative analysis to get a better result