In schedule risk analysis, what is the primary advantage of using three-point estimates (optimistic, most likely, pessimistic) over single-point estimates?
-
A
They eliminate all uncertainty from the schedule
-
B
They capture the range of possible durations and support probabilistic analysis
-
C
They reduce the number of activities needed in the schedule
-
D
They allow the scheduler to bypass stakeholder approval