What is a resource histogram used for in project scheduling?
-
A
Displaying the sequence of project activities over time
-
B
Showing resource demand per time period to identify over- or under-allocation
-
C
Tracking cumulative costs against the performance measurement baseline
-
D
Mapping team member skills to scheduled activities