A project's Estimate to Complete (ETC) is calculated as EAC - AC. This formula is used when:
-
A
Past performance is expected to continue at the current CPI
-
B
The original estimate is considered fundamentally flawed and a new estimate is prepared
-
C
All remaining work will be performed at the budgeted rate
-
D
The project scope has been reduced