A project manager observes that the critical path has changed after updating the schedule. What is the most likely cause?
-
A
A resource was added to the project
-
B
One or more activities on the original critical path gained float due to early completion
-
C
The project sponsor approved a scope reduction
-
D
A risk was retired from the risk register