A project is in execution when the customer requests scope changes that were not planned. Which process ensures these changes are evaluated for schedule impact before approval?
-
A
Develop Project Charter
-
B
Perform Integrated Change Control
-
C
Close Project or Phase
-
D
Estimate Activity Durations