A project manager is preparing a schedule status report for senior stakeholders. Which reporting format BEST conveys milestone achievement at a glance?
-
A
Detailed Gantt chart with all 500 activities
-
B
Milestone chart showing planned vs. actual milestone dates
-
C
Full network diagram with float values
-
D
Resource histogram for each team member