A project manager notices the SPI is 0.82 at the midpoint of a software project. Which action is MOST appropriate?
-
A
Close the project immediately
-
B
Analyze which activities are behind and implement schedule recovery actions
-
C
Increase the project budget to compensate
-
D
Report the variance to the customer only at project completion