A control account manager reviews a work package with SPI = 0.75. What corrective action is most appropriate?
-
A
Reduce the project budget
-
B
Accelerate work or add resources to recover schedule
-
C
Recalculate the BAC
-
D
Decrease the quality standards to speed up delivery