A PMI-SP professional is applying Monte Carlo analysis to a schedule. What is the PRIMARY output of this simulation technique for duration estimating?
-
A
A single deterministic project end date
-
B
A probability distribution of possible project completion dates
-
C
The critical path length in working days
-
D
Resource histogram showing peak usage