A project manager is estimating durations for a software integration task. The most optimistic estimate is 4 days, the most likely is 9 days, and the most pessimistic is 20 days. What is the PERT expected duration?
-
A
9.0 days
-
B
10.0 days
-
C
10.5 days
-
D
11.0 days