A project scheduler is analyzing a network and finds that Activity X has Free Float of 0 but Total Float of 5 days. What does this mean?
-
A
Activity X is on the critical path
-
B
Delaying Activity X will delay its immediate successor
-
C
Delaying Activity X will not delay its successor but could delay the project
-
D
Activity X has no scheduling flexibility at all