A project has four paths with durations of 22, 25, 25, and 18 days. Which statement about the critical path is correct?
-
A
There is one critical path of 25 days
-
B
There are two critical paths, both 25 days long
-
C
The critical path is 22 days because it has the most risk
-
D
The critical path cannot be determined without float values