Which change control process step ensures that a schedule baseline change is properly evaluated before approval?
-
A
Direct implementation by the project manager
-
B
Impact analysis reviewing cost, schedule, scope, and risk implications
-
C
Immediate update to the project schedule
-
D
Verbal approval from the sponsor