A project experiences scope creep that was never formally approved. How does this affect the schedule baseline?
-
A
The baseline automatically expands to absorb the extra scope
-
B
The baseline remains unchanged and actual performance will appear worse than planned
-
C
The baseline is voided and must be re-created from scratch
-
D
Scope creep has no effect on the schedule baseline