A project manager discovers that 15 approved change requests were never incorporated into the schedule baseline. What should be done first?
-
A
Archive the change requests and move on
-
B
Update the schedule baseline to reflect all approved changes and reissue it
-
C
Reject the change requests since the baseline is already set
-
D
Escalate to the sponsor without updating the baseline