A construction project requires that concrete must cure for 72 hours before framing can begin. This waiting period is best represented as:
-
A
A lead on the Finish-to-Start dependency
-
B
A lag on the Finish-to-Start dependency
-
C
A discretionary dependency with no duration
-
D
A mandatory Start-to-Start dependency